| - | ====== Non-working days ====== | + | ====== Non-Working Days ====== |
| <WRAP 100%> | <WRAP 100%> | ||
| <WRAP 400px left> | <WRAP 400px left> | ||
| - | {{gallery>:en:nonworking_day.png?direct&400|}} | + | {{:en:diary: |
| - | </ | + | In Buildary, the term **“Non-Working Day”** refers to a day that contains no data but is nevertheless a valid state. Examples include weekends or technological breaks |
| - | The term "Non-working day" is a day without | + | |
| - | The " | + | When you select a day, the drop-down menu on the right side of the window |
| - | A non-working day can be changed back to the working day, but only until the following day is not locked. | + | {{: |
| + | |||
| + | A Non-Working Day can be changed back to a working day using the same procedure. However, if the Non-Working Day has already been locked | ||
| + | |||
| + | Non-Working Days are indicated by a **gray underline** in the header. | ||
| - | Non-working days are underlined with the grey colour. | ||
| <WRAP clear /> | <WRAP clear /> | ||
| + | |||
| + | <WRAP tip> | ||
| + | Buildary does not allow you to lock a day with an electronic signature if it is preceded by a day that has not been electronically signed or has not been locked as a Non-Working Day. This is because the pages of the construction diary must be numbered sequentially. | ||
| + | |||
| + | Therefore, if a day is empty because no work was carried out on the construction site, mark it as a **“Non-Working Day”**. Otherwise, you will not be able to lock the subsequent days. </ | ||
| <WRAP info> | <WRAP info> | ||
| - | Buildary will not allow you to lock the day that precedes an empty or unlocked day. This is because the diary pages must be numbered sequentially. Therefore, the days must be locked one after another. | + | A day that has already been signed cannot |
| - | If the day is empty because there was no work on construction site performed, mark it as "Not-working day". | + | |
| </ | </ | ||